JUDGMENT OF THE COURT
1. Before us is an interlocutory appeal challenging a Ruling dated 20th March, 2018 by the High Court (Korir, J.) wherein the respondents preliminary objections with regard to the propriety of an application filed on 8th January, 2018 (the Application) at the instance of the appellants were upheld. As a result, the said Application by the appellants was struck out with costs which gave rise to the instant appeal.
2. In order to place the appeal in context, a brief background of the salient facts is necessary. The genesis of the dispute between the parties can be traced to rent arrears allegedly owed to Adinos AG (Adinos), a Swiss company by Viaggi Del Ventaglio (Viaggi), an Italian company. The arrears were in respect of premises which were leased out by Adinos to Viaggi in Switzerland. In a bid to recover the rent arrears, Adinos instituted court proceedings against Viaggi in Milan, Italy.
3. Thereafter, for some reason or another, Adinos by a cession agreement ass…