I. T. MUHAMMAD, JSC (DELIVERING THE LEADING JUDGMENT): The version of the appellant herein, as plaintiff at the Ogun State High Court of Justice, holden at Abeokuta (trial court), is that the plaintiff was a limited liability Company carrying on business, inter alia, as Building and Civil Engineering Contractors based in Abeokuta. In 1981, the plaintiff tendered for and was awarded a contract by the defendants, who are respondents, herein, for the construction of 25 kilometers road between Obafemi/Owode Local Government Area of Ogun State. The contract sum was ₦8,000,000.00 (Eight Million Naira). The plaintiff was put into possession of the Owode/Obafemi road site by the defendants and work commenced on the said project. The defendants agreed to pay mobilization fees of ₦1,600,000.00 (One Million, Six Hundred Thousand Naira). Contrary to the terms of the agreement, the mobilization fees were never paid by the defendants.
The plaintiff claimed that it suffered damages due to the failur…