JUDGMENT
INTRODUCTION
[1] The Plaintiff in this suit is a Limited Company engaged in among others facility management services 1st Defendant is a body corporate and is into acquisition of leases and provides estate management services among others. The Plaintiff and 1st defendant on 29 October 2018 entered into a Facility Management Service Agreement (FMSA) for it to provide reception, cleaning, security landscaping services and other maintenance services for a building known as Sloane House. The events which seem to have provoked the Plaintiffs’ present action are the allegation of breach of the FMSA and the failure of the 4th Defendant to pay for services rendered to him by the Plaintiff and an alleged breach of contract between the Plaintiff and the 3rd Defendant.
Plaintiff’s Pleadings
[2] The case of the Plaintiff as can be gathered from its pleadings is that on 29 October 2018 1st Defendant engaged Plaintiff to provide reception, cleaning, security, landscaping and maintenance servi…