RULING OF THE COURT
In a ruling before the National Environmental Tribunal in Tribunal Appeal No. NET 21 of 2019 the tribunal made several findings – it struck out some parties from the appeal finding them to be not necessary to the appeal; it struck out prayers relating to licences issued for development of previous premises; and a preliminary objection taken against a decision for change of user of premises was allowed. The main issue here relates to the grant of a prayer (v) fashioned by the tribunal as follows:
“The prayer no. 2 in the appellants application dated 14th August 2019 for stay of any construction in respect of phase 3 of the project be and is hereby allowed to preserve the status quo of the matter pending the hearing and determination of the appeal. This is in line with the intention of section 129(4) of EMCA which seeks to preserve the status quo of a matter or activity once an appeal is filed so as to safeguard, in the interim, the interest of any innocent purchaser o…