NYAGSI ENGINEERING LTD
V.
GHANA HIGHWAY AUTHORITY

(2018) JELR 63597 (HC)

High Court 15 Mar 2018 Ghana
BriefBot icon

BriefBot Summary

Free

- The case involves a breach of contract claim by the plaintiff against the defendant for general and punitive damages. - The plaintiff alleges that it won a competitive bidding contract to upgrade a road, but the defendant suspended the co

Case Details

Suit Number:Suit No. OCC/34/15
Judges:JENNIFER DODOO (MRS)
Counsel:L.N.S. AKUETTEH FOR PLAINTIFF,AYIKOI OTOO FOR DEFENDANT

Construction Contracts: Offer and Acceptance, Intention to be legally bound

Special Damages to be particularized and proven

Award of General Damages(factors to take into consideration)

Interest rates and how calculated

The Plaintiff’s claim against the Defendant is for general and punitive damages for breach of contract.

It was the Plaintiff’s case that in June 2007 it tendered for and sometime in 2008 won a competitive bidding contract to undertake the upgrading of the 54.2 kilometres Yendi-Gushiegu Road in the Northern Region of Ghana.

It averred that the Central Tender Review Board of the Ministry of Finance and Economic Planning gave concurrent approval for the award of the contract to it on 23rd December 2008. This was followed by a letter dated 5th January 2009 confirming the award of the contract at a price of GH¢35,994,052.54.

It was the Plaintiff’s case that the Defendant had demanded the provision of a performance security and had indicated that with this condition fulfilled, the c…