JUDGMENT
In an amended writ of summons filed on 21st February 2014, the Plaintiff claimed against the Defendant, the following reliefs:
a) The recovery of the sum of US$299,520.00 being 30% of the contract figure that still remains unpaid.
b) Interest on the said amount in (a) above at the bank lending rate till date of final payment
c) Special Damages in the sum of GH¢965,893.96.
d) Damages.
e) Costs
f) Any other relief (s) which this Honourable Court deems just and equitable.
It was the Plaintiff’s case as set forth in its Amended Statement of Claim that in it had fulfilled its part of a contract awarded it by the Defendant to supply 800 computers and UPS devices at a cost of $998,400.00. It averred that the Defendant had informed it that some of the software was not authentic and had continued to hold onto the outstanding balance of 30% of the contract sum.
It was also the Plaintiff’s case that it had to take 2 short term loans from Ecobank to fulfill its obligations under the contract…