TOTAL ENGINEERING SERVICES TEAM INC.
V.
CHEVRON NIG. LTD

(2017) JELR 56454 (SC)

Supreme Court 24 Feb 2017 Nigeria
BriefBot icon

BriefBot Summary

Free

- The dispute arose from a service contract between Chevron Nigeria Ltd. (respondent/claimant in arbitration) and Total Engineering Services Team Inc. (appellant/respondent in arbitration) following the abduction of a US national seconded u

Case Details

Suit Number:SC.185/2010
Judges:MARY UKAEGO PETER-ODILI JSC (Presided and Read the Lead Judgment) KUMAI BAYANG AKAAHS JSC KUDIRAT M. OLATOKUNBO KEKERE-EKUN JSC CHIMA CENTUS NWEZE JSC EJEMBI EKO JSC
Counsel:Adewale Atake (with him, Chidiebere Ejiofor, Solomon Babajide) - for the Appellant. -*- Adedoyin Rohdes-Vivour (with her, Anthony Onwaeze) - H -*- for the Respondent.

PETER-ODILI JSC (Delivering the Lead Judgment): This is an appeal against the judgment of the Court of Appeal, Lagos Division, Coram: C. B. Ogunbiyi, R. C. Agbo and A. Jauro

JJCA. In the judgment, the Court of Appeal or court below or lower court affirmed the decision of Adefope - Okojie J. (as she then was) of the Lagos State High Court, remitting a part of the arbitral award to the sole arbitrator, H. Odein Ajumogobia SAN for reconsideration and decision. The respondent herein was the claimant in the arbitration proceedings and the appellant was the respondent in the arbitration proceedings.

The award of the sole arbitrator was delivered on 23 April 2004, a portion of which award was in favour of the respondent but the arbitrator dismissed a significant part of the respondent’s claim.

On 21 July 2004, the respondent filed originating summons with supporting affidavit at the High Court of Lagos State seeking an order setting aside part of the arbitral award or an order r emitting tha …